Regina Road demolition - Procurement strategy for the demolition of tower 1 – nos. 1 to 87 (Phase 1a), and two adjacent blocks of maisonettes, nos. 89 to 99 and 101 to 123 Regina Road (Phase 1b).
RESOLVED to:
2.3 The Cabinet Member for Homes is recommended by the contracts and Commissioning Board to approve the procurement strategy for the procurement of the Regina Road demolition and clearance contractor, including asbestos removal, via a mini-competition under the Notting Hill Genesis framework for a duration of up to 12 months and with an estimated total value stated in the Part B report. The contract period will be dependent upon project progress.
As per Part A report.
As per Part A report.
Publication date: 24/09/2024
Date of decision: 24/09/2024
Effective from: 02/10/2024