This report will set out the outcome of the procurement process that the Council has undertaken in relation to the appointment of the Demolition Contractor for the Regina Road Regeneration Project in accordance with the procurement strategy approved by the Executive Mayor in Cabinet on 26th July 2023 ref: PB-2324-000005-S.

 

Decision:

2.1The Corporate Director of Housing is recommended by the Chair of CCB with the approval of the Cabinet Members for Finance and for Homes to:

 

2.2 approve the award of a contract for the provision of Demolition and Site Clearance Services for Phases 1a and 1b of the Regina Road Regeneration to a maximum value as stated in the Tender Report (Part B) to the Successful bidder (Supplier E) (identified in Part B)

 

2.3 approve that, in the event the first-place Bidder seeks to renegotiate the commercial terms of the contract, the award may be withdrawn from the first-place Bidder and awarded to the second-place Bidder (Supplier A) and for the contract value identified in Part B.

 

Reasons for the decision:

As per the Part A & Part B reports.

Alternative options considered:

As per the Part A & Part B reports.

 