The
Cabinet Members for Homes introduced the item and outlined details
in a
Presentation
Following the presentation, Members had the opportunity to ask
questions
In
response to queries raised by the Sub-Committee, the following was
clarified:
-
The Housing Improvement Board was an independently
Chaired Board with its own Terms of Reference which had undergone a
review with changes made to the TOR
-
The Membership of the Board was being looked at to
ensure appropriate reflection of representation of equality and
diversity
-
A number of other blocks had been identified as
having damp problems, with two of them being classed a
priority
-
A number of meetings had taken place with residents
to talk through issues
-
Analysis of historic allocations, to look at how
allocations had been managed and if the policy was fit for purpose
was an action in the Improvement Plan
During the consideration of the recommendations, the
Sub-Committee discussed the following:
-
In assessing what went wrong, in particular with the
issues at Regina road, it was acknowledged that there had been
serious failings in the system. There were serious lessons that has
been learnt and were taken forward as part of the redevelopment of
the strategy. The new Housing Improvement Board would hold all
aspects of the Council to account and it would be vital to ensure
that all work streams worked well in tandem and identify
interdependencies. Case work Management was an area of priority to
be addressed as part of the improvement work
-
To address the areas of concerns with the Axis
contract as highlighted by the Ark report, several joint
workshops with council and contractor staff at operational level had taken place with discussions
on all aspects of the contract as well as how adapted ways of
working as a result of the Covid
pandemic. The ideas captured as the sessions would be developed
into an action plan that would be fundamental to the Improvement
Plan.
-
The Action Plan would be finalised, project officers
had been identified for wok streams and this would be discussed at
the next meeting of the Tenants and Leaseholders Panel.
-
There were issues with current levels of vacancies
as a result of competitive market across London for experienced
Council and Housing Association officers. Contractors had also
experienced issues with recruitment as a result of Brexit which was
having and impact of their ability to retain staff. They were
however resourced at the level they should be based on the amount
of work they were expecting following data that was presented to
them by the Council that the beginning of the contract that they
had submitted their tender on the basis of.
-
There were block by block visits taking places
across the whole borough with efforts initially concentrated on
areas that were of similar concerns as Regina Road.
-
A Roadshow had commenced that would run till
September, starting at high rise blocks with lower levels of
engagement in an attempt to create more line of visibility through
a targeted knocking exercise to introduce/reintroduce officers to
tenants.
-
There was a lot of work to be done on communication
to residents that the information that had been gathered from them
was going into a planned process of work. Communication needed to
be more explicit going forward with residents as well as with Ward
Members.
-
Further work was needed on the complaints process ,
including training for staff on the definition of a complaint and
the management process
-
Council officers had approached London Councils to
identity which Boroughs were determined as exhibiting good practice
in resident involvement. Officers had approached those LA’s
to gain knowledge.
-
Through the Housing Strategy, officers had been
exploring avenues to identify available resources to drive forward
change. A number of Directors from London council, housing
associations and several organisations had come forward to feed
into the strategy
-
The Housing Improvement Board would act as a
representative tool for tenants and be a positive forum and would
act as an advisory group to the Council .This Board would be a
vessel for tenants to utilise to communicate their views and be
listened to.
Requests for information to be sent to the
Sub-Committee:
-
How much funding is spent on repairs (responsive and
programme repairs) on Wates blocks
-
Schedule of roadshows and engagement
-
Number of flats affected by damp related issues
across the whole council housing stock
-
Number of dispute cases against the council –
this year and 2-3 previous years as well as some clarification as
to how these link to monitoring of performance of the responsive
repairs service
-
Housing supply determination underpinning the
development of the housing strategy (supply from council housing /
housing associations / other)
-
A plan of the interdependencies between workstreams
Further meetings:
Responsive repairs contract management and monitoring framework
(incl. feedback from officer workshops) – planned for August
with Tenants and Leaseholder Panel
Voids – planned for September with Tenants and Leaseholder
Panel
Outcome of officer workshops to be provided at the July Tenants
and Leaseholder Panel meeting
Sub-Committee’s conclusions
-
The Sub-Committee welcomed the update provided on
the emerging housing improvement plan and was assured that the
emerging plan was on the right track.
It was noted that the pace of progress has been impeded by the
transition of the new executive director and some restructuring
within the service, but the Sub-Committee accepted that this work
was essential to ensure the right lines of accountability were in
place to underpin the improvement plan.
-
The Sub-Committee looked forward to the evaluation
framework being developed, once the Housing Improvement Board was
set up. In particular, the Sub-Committee was interested to find out
how it would link back to the Council’s wider improvement
plan and the Corporate Risk Register.
-
The Sub-Committee concluded that the 10 work streams
were well defined and appropriate to drive improvement (some
recommendations are put forward on the work streams by the
Sub-Committee below).
-
The Sub-Committee recognised the value of using the
work of the Tenants and Leaseholder Panel to feed into the
improvement agenda and would advocate this approach being embedded
into the new ways of working developed by the housing service,
incl. post-delivery of the housing improvement plan over the next
couple of years.
-
The Sub-Committee welcomed the work of the panel on
the development of a Tenants Charter which would be a great vehicle
to improve tenants’ understanding of the level of service
they should expect as well as their rights and
responsibilities. It was felt that this
would lead to a greater level of direct accountability between
tenants and the Council.
-
At a previous meeting of the Sub-Committee, there
was agreement that the ARK report failed to establish how/why/what
caused the inaction in response to case work put forward by local
councillors and/or MPs. The Sub-Committee remained concerned that
without a fit for purpose case management system, similar issues
could reoccur. It was welcomed that work had started on identifying
a new Case Work Management system and there was a clear process for
housing related case management in the meantime.
-
One of the main areas of concern identified by the
Sub-Committee was around communication and engagement. Although
initiatives had started to be developed and implemented, it was
felt that more work was need to ensure both residents and their
elected representatives were suitable notice of any
events.
-
The Sub-Committee warmly received the new housing
structure as it placed resident engagement at a senior management
level thereby creating greater and clearer direct accountability
lines on these matters.
-
The Sub-Committee felt that the Terms of Reference
(ToR) for the Housing Improvement Board
lacked important details and welcomed confirmation that the
ToR would no longer be approved at
Cabinet, allowing additional time for these to be refined (see
recommendations on this topic below).
-
The Sub-Committee noted the challenges within
Responsive Repairs Service, particularly in regard to recruitment
which had been impeded by covid and
Brexit along with having to compete with residential and commercial
sectors to attract staff. In light of this, the Sub-Committee
commended the prioritisation of gas safety works and the rapid
progress achieved in such a short period.
-
The Sub-Committee noted there would be an informal
meeting in August to undertake a deep dive on the responsible
repairs contract, which will be undertaken jointly with officers
and the Tenants and Leaseholder Panel.
Sub-Committee’s recommendations:
Communication and residents’ engagement
-
A communications and engagement plan was needed to
map out all the one-off engagement exercises as well as new
communication practices to be embedded in new improved ways of
working. That plan should be informed by involving the Tenants and
Leaseholder panel, incl. in the development of the new Tenant
Handbook.
-
Further consultation with residents was needed
during roadshow exercises, engagement with Residents Associations
and Tenants forums as well as through the Tenants and Leaseholder
panel to identify what they would like to see be made publicly
available to further enhance transparency on the progress of the
delivery of the housing improvement plan
-
Work was needed to improve communication with
tenants on planned works / planned surveys. Should work be delayed or the original stated
deadline missed (often due to reasons beyond officers’
control), tenants should be kept informed, so they do not feel that
it is a case of just nothing happening.
-
There needed to be better communication of the
responsive repairs contract’s social value, including
apprenticeships (opportunities and about the types of roles they
can lead to)
-
There needed to be better corporate definition of
complaint and improving understanding of it and streamlining the
complaints process and promoting it amongst council tenants and
leaseholders
-
It was recommended that support be given to the
initiative of the Tenants and Leaseholders Panel in the development
of a Tenants Charter
-
It was recommended that a diagram is produced to map
out the communication routes of case work / enquiry / complaints
/escalation process to clarify to councillors and MPs ways of
escalating urgent housing casework as current guidance provides a
10 day turnaround which was not adequate for urgent housing case
work.
-
Further consideration was needed on the
recommendation in Government’s Housing White Paper on the use
of technology and how it could be incorporated into one of the
workstreams of the housing improvement
plan. This should include:-
-
The exploration of best practice and existing
software packages on tenancy management, repairs and other housing
issues and any that are used for general housing
communications.
-
Consultation with the Tenants and Leaseholder Panel
meeting on use of technology to inform this work.
Housing
Improvement Plan Workstreams
-
It is recommended that a plan for the strategy
development in Workstream 1, including
indicative timescales, be developed and shared with the
Sub-Committee once available.
-
Workstream
7 should be expanded to include in its scope the
issue of buildings nearing the end of their life, with further
consideration given to how these options are to assessed including
in relation to the future of some Brick by Brick sites in the
vicinity of some of these buildings
-
Workstream
8 needs to address the issue of resourcing /
workload allocation & management within the service. Staff can
be given the right skills and cultural/behaviour training but if
their workloads are still unmanageable as highlighted in the Ark
report, they will be set-up to fail. This workstream should also include within its scope
long-term workforce planning and apprenticeships.
Board
Terms of Reference
-
Further work should be undertaken to consider best
practice on the set up of such Housing Improvement Board,
particularly regarding membership and review/consider the following
before finalising the ToR,
including:
-
Number of tenant representatives
-
Ensure that tenant representatives are not only from
formal Residents Associations and Tenants Forums as many areas
where the council has housing stock where there is no RA (no RA
criteria necessary?)
-
Backbencher representation and/or mechanism for
backbenchers’ input
-
Meeting observers
-
Webcasting of meetings
-
Holding meetings in a hybrid manner to enhance
inclusivity so that people with disabilities and / or caring
responsibilities can put themselves forward as board
member/observer
-
Term of the chair (elected/number of
mandates/criteria/skills, experience and behaviours
required)
-
It is requested that the revised ToR are circulated to the Sub-Committee before
approval and ensure ToR included as
appendix marked as draft in the cabinet report.
The Housing Improvement Board
once set up should be given a role to inform the budget setting
process (MTSF as well as HRA) and the upcoming HRA review (if
timings of review allow).